Side Deck Build

Niagara Falls, ON

Side deck build in Niagara Falls, replacing a weathered platform with new base prep and framing, grey decking, and white railing.

Weathered grey wood platform at the side door with boards missing, before the rebuild
Finished side-entry deck with grey composite decking, two steps and white railing
BeforeAfter

Drag the handle, or focus it and use the arrow keys, to compare before and after.

We replaced a worn-out side entry platform at a Niagara Falls home with a new deck built on a fresh concrete base. The finished entry has grey decking, three wide steps and a white railing that matches the house trim.

Project type
Side Deck Build
Location
Niagara Falls, ON
Photos
11 from the job site
Scope
Worn side platform replaced with a new entry deck
Base
Reinforced concrete pad and metal post bases
Finish
Grey deck boards and stair treads, white railing
Service
Deck building

From first look to final reveal.

Select a stage to jump to its photos.

  1. Weathered grey wood platform at the side door with boards missing, before the rebuild
    01BeforeOriginal platform condition
  2. Formed concrete pad with wire mesh and gravel base
    02Base StartConcrete and prep work
  3. Finished grey composite steps and landing
    03FinishDecking and stair work
  4. Finished side-entry deck with grey composite decking, two steps and white railing
    04RevealFinished railing view

A platform that had given up

The before photos show a low wood platform outside the side door with its paint flaking off and several boards missing. The frame sat on bare soil beside the driveway, and you could see straight down to the dirt between the joists.

A side entry like this gets used every day, often more than the front door. We took the old platform out and started from the ground up.

Rebuilding also let us fix the layout. The old platform had no railing and no proper steps, just a single drop to the driveway.

Formed concrete pad with wire mesh and gravel base
Formed concrete pad with wire mesh and gravel base

Pouring a base first

Before any framing, the crew formed and poured a concrete pad along the house. The photos show wire mesh laid across the gravel inside the forms to reinforce the slab, and a foam strip along the foundation wall so the new concrete can move without cracking against the house.

The pad gives the deck a flat, dry surface to stand on and a solid landing at the bottom of the stairs. Wood that sits on wet soil rots from the bottom up, which is what happened to the old platform.

Close-up of grey composite stair tread nosing
Close-up of grey composite stair tread nosing

Framing on post bases

The frame stands on short posts set into black metal post bases fastened to the concrete. The bases lift the wood off the slab so rainwater drains away instead of soaking into the end grain.

The crew built the rim and joists square to the house wall and checked the height against the door threshold so the top step lands flush with the doorway. Grey fascia boards wrap the outside of the frame.

Side deck build with grey decking and white railing — finished landing detail
Side deck build with grey decking and white railing — finished landing detail

Decking, stairs and railing

Grey deck boards run the length of the landing, and the stair treads use the same boards with a clean nosing at the front edge. The three steps come down toward the front of the house onto the concrete pad.

The white railing has square posts, caps and balusters at even spacing, with a sloped section following the stairs. White against the grey siding keeps the entry bright in a narrow side yard.

Snow and ice collect in a shaded side yard, so the railing runs the full length of the landing and down the stairs. You get something to hold every time you use the door in winter.

Questions about this project.

Something else on your mind? Ask us directly.

Why did my old side deck rot so fast?

Most small entry decks fail where the wood touches soil or stays wet. On this Niagara Falls job the old frame sat on bare dirt. A concrete base and raised post bases keep the new frame dry.

Can you build a deck in a narrow side yard?

Yes. This deck fits between the house and the driveway. We plan the stair direction around where you walk and make sure the landing clears the door swing.

Do I need a railing on a low entry deck?

The Ontario Building Code requires a guard when the deck surface sits more than 600 mm above the ground. Many owners add one on lower decks too, for a handhold on icy winter mornings. We talk through both at the site visit.

Planning something like this?

Tell us what you have in mind. We visit the property, look at the space with you, and put together a free quote based on what we actually see.